| Valley
High School - Site Design |
- On Budget
- 129,408 square feet of new space
- Program Goal is achievable
(4,400 square feet short as currently drawn but Commons shown
too large)
- 4 ˝ - 5 ˝ years of construction
(estimated)
- Flex space available to help minimize teacher/learning
disruption
- New “skin”/image to Woodland
- High identity main entrances (North and East)
- Offers additional E-W hall connector
- Re-uses some tunnels for piping only
- More “re-roof “ area than Plan 2
- Parking vs. green (effect on green worse than
Plan 2)
|
|