Valley Construction - September 2006

Update through September 14, 2006

Commons between the 2-Story and Field House

Most floor tile laid, still some grouting to take place. The restroom tile is in place and most plumbing finished. Still some privacy partitions to install. Painting is complete, banners installed. Punch list for this area scheduled for September 26. Main stairway tile being set on the steps.

2-Story
2nd Floor – Punch list has been created for the area and contractors are working their way through cleaning up items on that list. Move-in of furniture scheduled to start early October.

1st Floor – Most tile has been set, ceiling dropped in most rooms, still some to drop in the corridors. Still come carpeting to lay and ceiling tiles to drop in many of the classrooms. Much of the millwork has been set with still some tops to install. Still some doors to hang. Restrooms have plumbing fixtures set, however, still need privacy stalls, but that work is ready to take place. Punch list scheduled for 1st floor on September 26.

Exterior work is complete, punch list has been prepared and is in the process of being completed. Still some light poles to set.


 

Photo Galleries

September 14, 2006

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster