Commons area – Floor tile work has
started between the field house and the new two-story. Lockers
are in, signage has been hung, and most painting is complete.
Second floor – Corridor tile has been
laid and corridor ceiling grid is in place as are electrical
lights in that grid. Most classrooms have ceiling grid, marker
boards hung, and painting complete – still need electrical
trim. Elevator in and operational, air conditioning connected,
but not fully controlled as yet. Grinding and polishing on
Art Room floors complete. Most finish painting is complete
on second level. Tile, fixtures, and toilet partitions all
complete in upstairs restrooms. Carpet to start the week of
7/31.
First floor – Corridors have ceiling
grid, but nothing on the floor as yet. Most classrooms have
ceiling grid and light fixtures hung and most boards hung,
but still painting and trim work to do. Still working on some
ductwork on the first level. Tile work in restrooms on lower
level nearing completion. No fixtures or partitions have been
set as yet. East end of first floor Commons has the floor
tile in place. Restrooms have tile complete. Some fixtures
and partitions have been set.
1B – Work is virtually complete with
only small odds and ends left. Still need final Certificate
of Occupancy inspection, which is scheduled for 8/3.
Work continues on the fire sprinklers
in the southeast corner of the existing building and the schedule
is a bit tighter there, but all on schedule for Fire Department
walkthrough on 8/3. Air conditioning in the kitchen is nearly
complete with cleanup scheduled for the week of 7/31.
1st floor – The Commons between the
field house and 2-story are mostly painted out. All masonry
work in place as is all electrical fixtures. Prime painting
is mostly complete and some accent wall painting has been
started. Electrical and technology wiring still underway as
is some ductwork. Floor tile has just started in the restrooms,
but none has been laid in the 1st floor corridors as yet.
One of the South Commons restrooms has all floor tile and
wall tile set. Floor tile installed in the second restroom
with installation of wall tile in process.
2nd floor – Corridor tile all laid,
painting mostly complete, and millwork has started. Ceiling
grids in classrooms in place and most light fixtures have
been hung. Painting is underway in the south stairwells. Many
of the marker boards and tack boards have been hung. In the
restrooms, all floor and wall tile set, painting complete,
and partitions and fixtures have been hung. Some HVAC detailing
is underway. Floor grinding and polishing in the Art Rooms
is nearing completion.
1B (Infill of Tiger Court &
area between Field House and existing building)
Ready for move-in with furniture scheduled to be installed
any day. Still one issue with the sight lines that needs to
be determined once the furniture is in place before final
Certificate of Occupancy is issued.
Field House
Although not included in the scope of this contract, the new
field house floor has been laid, but still needs to have the
finish applied.
|