1C (New 2-Story)
Work is underway preparing for a final slab-on-grade pour
that’s scheduled for Monday (2/13). Exterior brick work
continues on the south side of the building and there is about
one more week left until that is complete, then they will
move around to the east side of the building. Interior block
work is scheduled to start on the 2nd floor the week of 2/13.
New doors are being installed at the south end of the Field
House.
Construction continues to move at
a brisk pace with the favorable weather.
1B (Infill of Tiger Court & area between Field
House and exiting building)
Most sheetrock is hung throughout this area. Taping is complete
and some prime painting has taken place. Stepped floors for
Business Ed. classes have been poured. Sprinkler piping is
underway throughout this section. Most frames for doors and
windows have been set. Ceiling grid installed in many areas.
Interior block and brickwork is complete and most has been
washed down. Work continues on electrical and mechanical equipment.
1C (New 2-Story)
All floor slabs have been poured with the exception of the
small piece connecting to1B and a small portion immediately
adjacent to the south entry of the Field House. Plumbing,
ductwork, and electrical all ongoing. Masonry work for corridor
walls and rest room walls is underway. Masonry and pre-cast
trim on the exterior of the south side of the building nearly
complete and work has now started on the east side of the
building.
Project is moving along nicely and
is a bit ahead of schedule. The intent is to move into 1B
in mid-July and 1C in December.
|