DISTRICT HOME
Construction HOME
Western Hillls Elem.

RELATED LINKS

Sales Tax

 
QuickLinks
About Us
Boundaries
Lunch Menu
Newcomer's Section
School Board
Transportation
Valley Construction - December 2004

Update through December 29, 2004

A great deal of work has taken place over the Winter Break. Most of the concrete work in the dock area has now been completed. One challenge has been the tie-in of the new sanitary sewer with the main line in 35th Street. Conflicts between the proposed bore under 35th Street and existing utilities that are in unexpected locations have caused some difficulty. The rerouting of a gas line to accomplish this should be complete on Friday, December 31, thus freeing up things to make the connection, which will then allow the balance of the sanitary sewer line to be placed back to the existing building. Block work continues on the new Chiller Room/Auto Repair Shop with the east wall nearly complete and several of the interior walls in process. Under floor plumbing in the Boiler Room is virtually complete and pads for the boilers have been poured. All joist reinforcement in the existing Metal and Wood Working Shops has been completed except for a couple of small areas and are expected to be complete yet this week. Block work is underway on the electrical room expansion at the north end. Walls and lid have been poured for the tunnel connection and extension north of the existing Mechanical Room. Removal of the underground tanks is scheduled to start next week. Much plumbing, mechanical and electrical work involved in prepping areas for future tie-ins is being done while certain areas of the building can be taken offline for short periods over the Winter Break.

Update through December 17, 2004

Block work is underway on the new building. The block that had been laid on Friday, December 9 was blown over by strong winds on the weekend, so cleanup and reconstruction of that portion has been underway this week. Conduit for the main electrical lines has been run up to the building. Much of the work in the dock area has been completed with some paving that needs to be completed. The walls have been poured on the new connection to the tunnel on the north side of the existing mechanical room. All the under floor plumbing in the existing auto shop, which is now going to be repurposed as a mechanical room, and plumbing and valves for connection to the new boilers are in process. Removal of the underground fuel oil storage tanks is scheduled to commence the week of January 3. Also, the new sanitary sewer line from the new building to the connection at 35th Street is scheduled to be installed over Winter Break, so as to minimize interference with parking and traffic flows in the parking lot. New water service is scheduled to be switched over this weekend (12/18).

Update through December 10, 2004

Work continues on the underground water line installation as they now cut across the existing parking lot. It is expected that work will be complete very soon. The new sanitary sewer still needs to be installed and that work will commence in the next couple weeks. Most of the work around the dock and recycling area has been completed and repaving will happen there in the next few days, as weather permits. Joist reinforcement continues as rooms are available during non-class times. Electrical and plumbing upgrades are occurring in the existing tunnels. Most of the underground in the existing auto shop has been completed. New vault walls have been formed and are expected to be poured next week.

Update through December 3, 2004

Work continues on the new water line that is now stubbed into the mechanical room and connection at 35th Street has been made. Filling in the gaps of the water line is underway, with the schedule to cut through the parking lot next week and connect it to the building by week’s end. The storm sewer is in. Installation of the sanitary sewer is scheduled to follow completion of the water lines. The majority of the underground plumbing in the new chiller room and shop has been completed and work is scheduled to start on laying block next week. Work continues in the dock and dumpster area, with most of the walls now poured. Repaving of a portion of that area should take place next week. Underground plumbing work in the existing building that will also be part of the chiller room has mostly been installed. Work continues on the joist reinforcing. Engineers are still finalizing some issues with regard to the shoring for the building so that the underground tanks can be removed. It is hopeful that the tanks can actually be removed sometime this month.

Photo Galleries

December 29, 2004

December 17, 2004

December 3, 2004

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster