Valley Construction Update 07/11/07
Capitol Resources
7/11/2007
geneserg@wdmcs.org

page 1 of 2 Next

Demolition of west portion as of late June East entry Grading and soil removal at Woodland & Valley West Drive Grading west parking lot Installing storm drain lines NE corner of building
Demolition of west portion as of late June.jpg East entry.jpg Grading and soil removal at Woodland & Valley West Drive.jpg Grading west parking lot.jpg Installing storm drain lines NE corner of building.jpg
Loading excess soil Looking north at parking lot entry at Sylvania and Valley West Drive New NE corner ready for enclosure New bus lane parrallel to Woodland New main entry from Woodland
Loading excess soil.jpg Looking north at parking lot entry at Sylvania and Valley West Drive.jpg New NE corner ready for enclosure.jpg New bus lane parrallel to Woodland.jpg New main entry from Woodland.jpg
New north wall New parking at south end of existing east parking lot North parking lot North parking lot grading North side looking towards new main entry
New north wall.jpg New parking at south end of existing east parking lot.jpg North parking lot.jpg North parking lot grading.jpg North side looking towards new main entry.jpg