DISTRICT HOME
Construction HOME
10-Year Plan
Fairmeadows Elem.
Valley High School


RELATED LINKS

Sales Tax

 
QuickLinks
About Us
Boundaries
Lunch Menu
Newcomer's Section
School Board
Transportation
Construction Updates - August 2003

Stilwell Junior High
Reworking the screening to hide the mechanical equipment on the roof is the only item to be completed. The original design of the screening did not meet to the satisfactions of city requirements. Designers and contractors are working to obtain the least expensive alternative to meet these requirements.

Valley Stadium
The north end goalpost net has been erected. Screening for the mechanical equipment on the locker room roof is still an item of discussion with the city. All other items are warranty items at the stadium.

Hillside Elementary (See Hillside Updates)
Grading is complete and the majority of the foundations have been placed. They have discovered old foundations and some tile containing piping wrapped with asbestos in a small section of the west wing. Solutions have been identified, however, it is causing delay to the project in this area. Most of the underslab utilities are in place and work has started on the floor slab for the east wing. The off site storm sewer has been installed and is ready for our connection at the manhole in the street. The on site storm sewer work is complete on the north end of the site, but work still remains to be completed at the south end. Parking lot work at the Walnut Creek site is scheduled for this week and work on the street widening is also scheduled for this week. Precast and structural steel are scheduled for arrival the week of August 25.

Valley High School
The Site Design Team continues to meet on a regular basis and has narrowed the number of options to two. As soon as a plan has been agreed upon by this group, work will start with the city to further define the on and off site requirements for items, such as traffic, storm water retention, parking, etc.

Clive Elementary
Design development is 50 percent complete. The goal is to complete all documents and have them ready for the bidding process in February, so construction may start immediately after school is out in 2004. Since the creek straightening project was not acceptable to adjacent property owners, work is underway to determine how best to bridge the creek and use the area owned by the district on the west side of the creek for additional playground space.

Jordan Creek, Westridge, Phenix and Valley Southwoods
Structured cabling was installed in all of these schools this summer. Fire alarm systems have been updated in all the schools, except Phenix, where it was replaced. All work is scheduled to be complete in the next few days.

Fairmeadows and Indian Hills
Later this fall, proposals will be taken for a design firm to lead the remodeling effort for these schools.

Districtwide
Work continues on the design and installation of the fiber optic loop that will connect all facilities in the district. The project is slightly ahead of schedule. Work is also underway on the new phone system, which is slightly behind schedule. Work is also underway on the renovation of the new area for the Operations and Maintenance Facility and a large cooler/freezer area for food storage.

PHOTOS

Hillside Elementary

 


About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster