Hillside Construction - November 2003

Through November 20
Paved approaches to Eighth Street are being poured today. Striping on Eighth Street is scheduled for tomorrow. Most of the precast for the north side of the west wing has been placed, with only the southern side of that wing remaining to be installed. The majority of the steel has also been placed in the west wing, with approximately half of the wing’s roof joists in place. The metal stud work necessary to enclose the masonry portion (of the openings in precast) will follow the precast installation and is underway on the north side of the east wing. Studs, along with the backing board for the masonry, have been installed in most areas of the west wing. Radiant floor heating is installed in approximately one-half of the second floor of the east wing and the concrete will be poured either late this week or early next week.

Air-handling units have arrived on site and are being set today. This will allow the completion of the roof deck over the center wing, with the roofer scheduled to start on that area the week of November 24. The roofer will then move to the west wing and then proceed to the east wing. Interior load-bearing masonry walls are still under construction, with work this week continuing in the mechanical area and on the elevator shaft. Significant amounts of electrical conduit have been placed in the center wing. While it was expected that the balance of the parking lot would be paved this week, it was not completed and that work is on a day-to-day basis – dependent upon the weather.

Through November 13
Paving on Eighth Street is complete and the curb backfill is underway. Grading which will allow placement of the last street approach and the balance of parking has begun. Precast is near completion on the center and east wings and steel erection has started on the west wing. Second floor steel is partially complete on the east wing. Most of the first floor slabs have now been completed with the exception of small infill areas. The mason continues to work on interior walls and is currently working in the mechanical area. Most of the second floor deck for the east wing has been placed and some of the roof support steel has also been placed. Installation of in-floor radiant tubing for the second floor has started. Work on the east wing roof deck will start soon and roofing on the center wing is scheduled for the end of November. Most of the roof deck is in place over the center wing.  Electrical conduit is being placed in the center wing. Exterior wall studs are installed in the center and east wings. Roof deck is also in place over the office area.

November 25

West Wing

West Wing

Heat Tubes

Second floor metal deck and radiant heat tubes

Bus Drop Off

Bus drop-off looking south toward Hillside Avenue

East Wing

East wing

South Entrance

South (Hillside Avenue) Entrance

Dining Room

Dining room looking north toward kitchen & mechanical room

 


About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster