Hillside Construction - July 2004

Update through July 29, 2004

Most site landscaping is in place with the exception of a few trees that need to go in the parking lot areas. Seeding of the area north of Walnut Creek is still underway and sod will be laid around the building late next week. The west wing is virtually complete with a punch list being created for minor items that need to be tweaked. In the center wing, carpet and millwork have been installed in the Administrative area and carpeting is scheduled to be laid in the Media Center yet this week. Installation of translucent panels around the Reading Room is now underway. Vinyl tile flooring in the entryway is scheduled to be done next week. The dining room floor has been placed, cleaned, punched, and protected and now chairs for the classrooms are being stored in that area. The tile on the east wall of the kitchen has been installed and the final pieces of kitchen equipment are being set. The gym is painted and the floor is scheduled to be poured on August 9. The art room is being used as a storage area for wall shelving. The shelving is now being installed in the west wing. In the east wing, all the carpet is laid, however, not all decorative inserts have not been installed. Most sliding glass doors and overhead doors are in place. There are still some small pieces of millwork to place. The ceiling tiles have been dropped and finish painting is underway. The elevator is complete and ready for inspection on August 2. The east wing is scheduled for the start of punch list on August 3. The center wing punch is scheduled for August 6. A walkthrough with the Fire Marshall is scheduled for August 5. Fencing of play areas should commence very soon.

Update through July 22, 2004

More landscaping has been done with most of the shrubs around the building in place and several of the trees planted on site. Work is underway on readying site lighting poles. The balance of the concrete in front of the building has now been poured. Most of the carpet is installed in the west wing and most finish painting is complete in that area. Millwork installation is underway in the center wing with most of it installed in the administrative area and bookshelves are being installed in the media center. Much of the finish painting has also been completed in this wing and in the gymnasium. Ceramic wall tile is now completed in the kitchen, which will allow setting of the final pieces of kitchen equipment. Dining room floors are being cleaned and ready for turnover so that the area can be protected and used as an assembly area for furniture. The same is true of the art room, which is nearly complete and will be punched and ready for assembly of furniture. Most millwork has been set in the east wing and plumbers are still involved in installing their work in this wing. Rollup and sliding doors are also being installed in the east wing. Most ceiling tile has been dropped and the majority of the vinyl flooring has been installed, although some remains to be completed on the second floor. Elevator work is one day from completion and the elevator inspection has been scheduled for August 2. Work continues on electrical and low voltage wiring throughout the building although primarily in the center and east wings.

Update through July 15, 2004

Most concrete work is complete with the exception of a very small portion in front of the building slated for replacement. Landscaping is underway. Pea gravel and sand around the play equipment has now been installed. Roof edge trim detail and soffit work are underway on the perimeter of the building. HVAC units are up and operating. Ceiling tile is being dropped in the west wing with most of it complete. Carpet installation is scheduled to start in the west wing next week and finish painting is also underway in that wing. All doors have been hung in the west wing, the first floor of the east wing, and in most of the center section of the building. Sliding doors and roll-up door installation has also started on the first floor of the east and west wings. Vinyl tile work is now underway on the second floor. Furniture is being delivered to the warehouse, and in the next week, furniture assembly should be underway. Elevator work is now scheduled to be completed next week. Lights are being installed both floors of the east wing and in the gym. Painting is underway in the gym. Millwork and plumbing continues to be installed on both floors of the east wing and is nearing completion in the west wing.

Update through July 8, 2004

All play structures have now been installed. One section of driveway in the parking area has been removed and should be replaced in the next few days. The play structures still need pea gravel and finishing touches. Most of the finish grading is complete. There are areas that still need to be seeded on site, as well as the north side of Walnut Creek. That work should be done soon. Landscaping is also scheduled to start in the next few days. The majority of the plumbing fixtures are now installed in the west wing and work is underway on plumbing in the east wing. Doors have been hung in the west wing and hardware is being installed. Door hanging is now underway in the center wing. The west wing is ready for dropping of ceiling tile and laying of carpet tiles as soon as the humidity is fully under control, which should be early next week. The dining room floor tile is complete and installation of ceiling grid and lighting is underway in that area. The corridor floor tile is complete on the first floor of the east wing and is now underway in the living room areas on that level also. Millwork installation is underway on the first floor of the east wing. The elevator installer will be back to finish the work on the elevator in the near future. Most toilet partitions and plumbing fixtures have been installed in the restrooms on both floors of the east wing. Chillers and air handlers have been started and are still being adjusted. That is expected to be under control early next week. Some furniture has started to arrive and is being staged and assembled at the Operations Building.

Update through July 1, 2004

The site work continues with most of the play structures installed. Some of the sidewalk gaps have now been poured and concrete work for the play structures is underway. Site prep and seeding is nearly complete now in the northeast corner of the site. Plumbers have started installing sinks and fixtures in the west wing and have some of the fixtures set for the main restroom on the first floor. Installation of cubbies and window trim on the west wing is well underway. Some installation of millwork has started on the first floor of the east wing and in selected areas in the center section. Tile is complete in the west wing and is being laid in the east wing starting at the east end and working toward the center. Some floor leveling is underway in the dining area and tile work in that area is expected to start yet this week. The chillers and air handlers have been started and are being tweaked, but generally they are able to keep the building temperature under control. As soon as the humidity is under control, ceiling tile will start to be dropped in place. Most electrical fixtures for the west wing are in place, as well as a good share of those on the first floor of the east wing. Doors are now being hung in the west wing. Painting is happening in selected areas as they become available. Much of the elevator work is complete and it is expected be finished next week. Toilet partitions have been installed in the first floor restrooms in both wings, but that work remains to be done on the second floor of the east wing. Site work at Walnut Creek has been completed with the exception of the seeding.


About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster