Work continues on the roof as weather allows. The steel issues that
have delayed the roofing have now been resolved. Work is underway
on the dining area roof and should be complete very soon. The majority
of the west wing has been roofed and a second roofing crew will
be added next week. This crew will start on the east wing, the goal
being to have both the east and west wings completely roofed by
the end of the week of January 19, leaving only the roof for the
administrative area and the mechanical room to be completed the
week of January 26. Work continues on the exterior steel erection
and that work is expected to be complete the middle of next week.
The interior burnished block work is complete in the west wing and
very near completion on the first floor of the east wing. Masonry
work will start on selected areas of the exterior next week. Work
continues on the plumbing and mechanical rough in throughout the
building. Stairs are now scheduled to be on site in late January.
Interior wall framing for the second floor east wing is scheduled
to start next week.
The weather has slowed progress on the roof, but work has now resumed.
As previously noted, the roof over the gymnasium and media center
is complete and they are currently working on the roof for the west
wing with the majority of that now scheduled to be completed soon.
The roofers will then move to the east wing and then to the final
area to be completed over the dining room and mechanical room. Issues
regarding steel details have been resolved and roof deck is complete
in most areas. Studs for interior walls in both the east and west
wings continue to be placed and work continues on enclosing the
exterior walls on the second floor of the east wing. The masons
are installing non-load bearing block walls and burnished block
in the east wing and expect to start soon on portions of the exterior
block. Mechanical, electrical, and plumbing work is well underway
with significant amounts of plumbing and electrical rough in placed
in the west wing. A majority of the duct work for the gym has been
installed. Final framing for the east wall of the dining room is
now being placed. Delivery of metal stairways continues to be delayed
and is now scheduled for arrival late in January. The most critical
element to be completed at this time is the roofing and dry weather
is the key as the roofers move toward getting a roof over the entire
structure.
|