Hillside Construction - December 2003

Through December 31
The roof over the gymnasium and the media center is now complete to the stage that all beneath remains dry regardless of the weather. Roofers continue to work on the west wing and should be nearing completion soon. They will then move to the east wing and the dining room/mechanical room portions of the center wing. There have been some delays due to steel details which have now been resolved. That steel is being placed on Friday, January 2 and this will allow completion of the roof deck so the roofers can continue with their work. A portion of the opening on the second floor east wing has now been framed so it is ready to be enclosed. Interior walls for the first floor of the east wing have all been studded and work is underway in the west wing installing studs for interior walls. Work continues on the rough-in for mechanical, electrical and plumbing throughout the building. The metal stairways have not been delivered and are approximately two weeks out. Temporary heating is being used in the lower level of the east and west wings, as work on the interior walls and various portions of masonry continues.

Through December 18
The west wing, center wing, and lower level of the east wing have all been enclosed. The interior wall framing and furring of exterior walls in the lower level of the east wing will be complete soon. Framing of openings for the second floor of the east wing is underway. Roof deck has been placed on all of the building with the exception of the east wing. Two bearing masonry walls for the east wing need to be completed and work is underway with the expectation that both will be completed in a week. This will then allow for the installation of the balance of the roof deck. Roofing is underway on the center wing and is approximately one-third complete on that wing. With good weather (temps above 17°F, little snow, and no high winds), this section should be completed by the end of December. The roofers will then move to the west wing. An additional crew will be added around the first of the year to finish the roof work. All floors in the building have been poured with these exceptions – a small portion of the second floor of the east wing, the stage area of the dining room, and the teachers’ workroom. Those areas will be finished as soon as the building is completely heated. Rough-in of electrical and mechanical systems continues throughout the building. The metal stairs are scheduled to be delivered in the very near future, and final steel placement and framing of the office area has also been scheduled. The small, unpaved portion of the parking will be poured in the spring. The lower level of the east wing and the west wing are now heated, which allows for more productive performance of the rough-in. As soon as all roofing is in place, the insulated heating and cooling ducts will be installed.

Through December 4
All the approaches on Eighth Street and most of the parking lot have now been poured. However, there is one small section of parking lot that remains and weather permitting, it will also be completed before spring. All of the precast has been set and the final pieces of steel are being placed on the west wing. Roof deck for the west wing should be placed soon. Areas that have masonry are being enclosed with metal studs and backing material and most of that work is complete on the center wing and the lower level of the east wing; and is now underway on the west wing. A portion of the floor deck for the second floor of the east wing has been poured and the remainder is scheduled to be poured next week. The roof deck is on the center wing and the roofer has started. However, the snow has temporarily halted work. Significant amounts of mechanical and electrical work have been placed in the center and east wings and work continues on interior block walls as weather permits.

December 24

East Wing, Second Floor

East wing of second floor

East Wing, Corridor

East wing corridor looking west

Interior Studs

Interior studs at east wing

West Wing

West sing looking west from second floor of east wing

December 8

Center Area

Center area looking northwest

Gym

Gymnasium and administrative area looking south

North Wall, East Wing

North wall of east wing looking east

Media Center

South wall of media center

West Wing Corridor

West wing corridor looking southwest

 


About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster