Hillside Construction - August 2003

Through August 28
The parking lot grading is mostly complete and forms are being placed and the first concrete pour is expected to happen late this week. Grading is also underway for the Eighth Street widening. The power poles will be removed next week, with paving to immediately follow. The Walnut Creek parking lot has been paved, but some approaches and curbs need to be placed. That will take place after the power pole is moved. Asbestos removal is complete. The necessary work on the footing modifications and helical pile is underway and should be complete this week. This will deal with the rubble found at the southwest corner and allow the footings to be completed. Preparation for the east wing floor slab is underway and the radiant heat pipes for approximately one-third of that east wing are in place. The first floor slab pour should happen next week. Pre-cast and steel delivery is scheduled to start in early September. A second erection crew will be added in mid-September to speed the process. Most of the site utilities on the south portion have been placed and connection in the street should happen in the next few days.

Through August 21
The additional parking lot work for Walnut Creek has been paved and the striping and curb details are being addressed. Grading for the main Hillside parking lot is underway and paving is expected to start next week. Preliminary work for the Eighth Street widening has started. Several light poles will be removed in the next few days and then the actual widening itself will begin. The discovered asbestos is being removed. Unfortunately, the material is brittle which slows the removal process. If the situation doesn’t improve, it may take another two weeks to complete. Preparation for the floor slab for the east wing is underway and work on the radiant tubing that goes in that slab will start next week. Some masonry work should also start next week. Pre-cast and steel delivery and erection will start in early September and by mid-September a second crew will be added to expedite that process.

Through August 13
Grading is complete and the majority of the foundations have been placed. Work has started on the east wing floor slab. Old foundations and tile containing piping wrapped with asbestos has been discovered in the west wing’s southwest corner. Solutions have been identified, however, it is causing delay to the project in this area. Work on reducing the asbestos will start on Aug. 18 and could take as long as three weeks, depending on what is discovered as the piping is uncovered. The most economical solution for dealing with the old foundations has been determined to be helical piles. That work should also start later in the week of Aug. 18. The off site storm sewer has been installed and is ready for our connection at the manhole in the street. The on site storm sewer work is complete on the north end of the site, but work still remains to be completed at the south end. Parking lot work at Walnut Creek is underway with paving scheduled for later this week. The Eighth Street widening will immediately follow the paving. Precast and structural steel are scheduled for arrival the week of August 25. While delays are occurring on the west wing due to the asbestos, the overall schedule has not been compromised, just the sequencing.

Through August 6
Work continues on the east wing footings, with exterior and interior footings to be complete later this week. Most footings for the center wing are also complete and should be done early next week. The west wing exterior footings are nearly complete, but are stalled due to debris from old foundations that affects one small portion in the southwest corner of the building. A lay tile that runs for nearly 200 feet down the center of this wing affects the interior footings. This tile contains a couple of pipes and some questionable insulation and will need to be removed. Most underground work is complete in the center wing and is underway in the east wing with completion scheduled for next week. Work on the slab in the east wing should start the middle of next week. Most of the onsite storm sewer work on the north portion of the property is in place and installation of the south portion will start next week. The offsite storm sewer and water line in Eighth Street are nearly complete and should be ready for connection to our site in the next couple of weeks. Work should start on the Walnut Creek parking lot next week so it is ready for the start of classes later in August. Precast and steel production are underway with the first deliveries of precast scheduled for mid-August and steel in late August.

August 28

East Wing Prep

East wing preparation

Radiant Tubing

Room 1216 - radiant tubing installation

Setting Forms

North parking lot - setting forms

Storm Pipe

South side - storm pipe installation


August 15

Foundations

East wing foundations and underslab


August 12

East Wing

East wing column spread footings and underslab

Electrical Conduit

Electrical conduit from transformer to inside building

Mechanical Room

Mechanical room underslab piping, looking north

 


About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster