Fairmeadows Construction - September 2005

Update through September 30, 2005
Parking lot expansion has been poured. Masonry is underway on all new additions and bump-outs. Steel is on site and should be ready to set next week. Support steel for the mechanical plenum is on site and some is on the roof. Work is underway cutting holes for plenum roof supports in existing high roof areas. Work continues on plumbing and electrical throughout the building. HVAC duct work has started in the east wing. Grading for water retention has been completed.

Update through September 13, 2005
Site prep is ready for expansion of the parking lot. That work is scheduled for later this week. Slabs have been poured for all the room expansions and masonry work is scheduled to start later this week. Sewer line in the east corridor has been installed and the floor slab has been replaced. The equipment pads have been poured in the mechanical room and prep is underway for the new rooftop plenum that will distribute heating/cooling and ventilating air throughout the entire building.

 

Photo Galleries

September 30, 2005

September 13, 2005

 

 

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster