Fairmeadows Construction - July 2006

Update through July 28, 2006
Replacement windows for the front are in town and being assembled. They should be installed the week of 7/31, which will then allow the installation of the final exterior panels beneath these windows. Punch list items are nearly complete. All in all, everything is nearly buttoned up and should be shipshape for the opening of school.

Update through July 5, 2006
Majority of the work complete with primarily some punch list items still to be completed. Permanent windows are scheduled to be shipped on 7/7 and installed either the week of 7/10 or 7/17. That will allow the final exterior finish pieces on the building to be completed. All trailers have been removed from the jobsite. Commissioning of the HVAC system is underway and nearly complete. The final inspection of the fire sprinkler system is scheduled for Thursday, 7/6. All punch work should be complete prior to the end of July.


 



 

Photo Galleries

 

 

 

 

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster