Fairmeadows Construction - August 2005

Update through August 30, 2005
Grading has taken place for the parking lot expansion, as well as the required storm water detention. Footings for the expansion of the building, as well as the new third grade room have been installed. Work is underway on laying the first couple of courses of masonry so that floor slabs can be poured. Boiler has been removed, as has most other mechanical and electrical systems that are to be replaced. Sewer line work has commenced, with floor sawed and pipe installed and is in the process of being backfilled. Most of the prep work is complete for the new mechanical roof plenum. Steel scheduled to be delivered later in September.

Update through August 12, 2005
Most of the demolition has been completed. Interior doors have been removed and are set aside for refinishing. Piping and mechanical equipment is arriving. Areas have been cleared for the expansion of the new Kindergarten rooms, construction of the new third grade room and the new Music Room. Areas have been cleared for the expansion of the parking lot also.




 

Photo Galleries

August 30, 2005

August 12, 2005

 

 

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster