Exterior masonry on the south addition
should be complete very soon. Iron workers have started laying
the roof deck for the south addition and working on the supports
for the mechanical plenum that runs over a portion of the
existing building. Most door frames and window frames are
now on site. Scaffolding for exterior masonry is in place
for a portion of the existing building and connection to the
new northwest section. The goal is to have all the roof deck
on the south addition and the mechanical plenum framed within
the next week so that steel work can start to support the
second floor of the northwest addition. Under floor plumbing
lines are complete in the Mechanical Room area of the northwest
addition. All block work is complete for the elevator shaft
and stair tower for the northwest addition. Issues regarding
delivery of a few miscellaneous steel items and some iron
work manpower issues have slowed the pace from what was expected
this week. Both issues are being resolved.
Masonry work is now focused on the
elevator shaft and stair tower for the northwest addition.
The hole has been cut for the corridor from the existing entrance
to the new north addition and most of the block work on the
existing building has been completed. Work continues on the
mechanical plenum with structural supports being installed.
Under floor plumbing in the northwest addition is underway
and some additional walls for the connection to the existing
building on the south are in the process of being framed and
poured. Switch gear has been moved to the electrical room.
Most of the work in the last week has focused on the north
addition.
All steel roof joists for the south
addition have been set. The steel deck has been set in piles
on the roof, but not distributed. It should be installed next
week. Split-faced block skin for the south addition is complete
on the west side and approximately half done on the south
side. Brick face for the east side should commence next week.
Framing for the roof mechanical plenum will also start next
week, as most of the demolition needed prior to that activity
is now complete. Interior block work on the north addition
is underway, as well as on the connection of the new north
addition to the existing entry. Footing pads for the north
addition are now poured. All steel is on site and switch gear
has been delivered and is scheduled to be installed the week
of October 4. Resolution has been reached with regard to site
configuration and the redesign will be complete early the
week of October 4. That will move the south parking lot closer
to the street and modify the northwest turnaround. These changes
were necessary in order to maximize the green play space on
the east side of the creek. The west side of the creek will
be utilized for learning functions; however, it will not be
a play field at this time.
|