DISTRICT HOME
Construction HOME
Western Hillls Elem.

RELATED LINKS

Sales Tax

 
QuickLinks
About Us
Boundaries
Lunch Menu
Newcomer's Section
School Board
Transportation
Clive Construction - November 2004

Update through November 26, 2004

Progress has been slow due to the holiday break and also because windows have not arrived as scheduled. Some duct work continues and new electrical service has been brought to the building and a new transformer set. Work continues on the mechanical and electrical revisions in the mechanical room. The majority of the south wall of the north addition has been placed. Masonry is being scrubbed and cleaned and scaffolding is being removed. Backfill between the east end of the north addition and the new building is completed and the foundations for that area have been poured. Also, foundations for the stair tower on the west end of the north addition have been poured, as well as the floor slab for the mechanical room on the first floor. It is doubtful that the south parking lot will get placed before Spring.

Update through November 19, 2004

Duct work continues on the south addition. Roofing is being applied to the mechanical plenum and front entry. Mechanical plenum is now enclosed with plastic to allow work in inclement weather. The majority of the floor deck for the second floor of the north addition has been poured. There is still some steel and decking to be installed on the far west end. Masonry for the second floor walls on the north addition is in process. Backfill around the majority of the north addition has been completed. Work has started on sections of the firstt floor on the north addition. Work is underway on the new electrical service and the connection to the existing switch gear.

Update through November 12, 2004

The roof has been installed on the south addition and duct work has started in that area. Windows are scheduled to arrive mid-November. A portion of deck for the second floor of the north addition has been poured. The majority of steel for that floor has been installed and metal deck placed. Mechanical plenum has been framed and metal deck has been applied. Roofing will go on that area later next week. The entryway has been re-roofed. Masons have started laying block for the second floor walls on the north addition. South parking lot grading is complete and now ready for paving, hopefully before winter sets in. Electric switch gear is now set in place and electricians are working on making connections. Existing boilers have been re-fired to keep a minimum level of heat in the building. Underground walls for the north addition have been waterproofed and backfilling has started.

Update through November 5, 2004

Wet weather and defective steel have slowed the progress a bit, but all is now back on track. The south parking lot is scheduled to be graded and the relocating of any necessary utilities will also be done – the goal to have it paved before the asphalt plants close down for the winter. All roof deck is on the south addition and roofing has started with approximately half of the roof to be dried in today and the balance by Monday. Roofers will then move to the main entrance area. Framing for the mechanical plenum has started with the expectation that it will be available for the roofers later next week. Framing and decking for the second floor of the northwest addition is about 50% complete. The first pour on that level is scheduled for early next week with the second and final pour scheduled for late next week, weather permitting. Masons have most of the finish material on the first floor of the northwest addition, as well as the southerly connection of that addition to the existing building. Windows for the south addition are scheduled to arrive mid-November.

 

 

 


Photo Galleries

November 26, 2004

November 19, 2004

November 12, 2004

November 5, 2004

 

 


   

About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster