Clive Construction - March 2005

Update through March 28, 2005
Finishes are underway in the south addition with some painting complete and many of the ceiling tiles dropped in place. Work continues in the north wing with prime painting complete on the first floor and underway on the second floor. Ceiling grid and lights have been installed in most first floor classrooms. Pans for the stairs and landings have been poured. Some sprinkler work is continuing. Piping and electrical work in corridors continues and piping installation in mechanical areas is underway also. Skylights have been installed in the Art Room. Millwork has started to arrive on site. Lights and ceiling grid have been installed in much of the existing building. The majority of the masonry work is complete, although a small portion remains to be completed at the entrance to the gym. Grading for the parking lots is scheduled to start later this week, weather permitting. Most of the tree work has been completed for the walking path on the west side of the creek. The bridge has been bid and awarded and that work will take place in late June and early July.

Update through March 16, 2005
The south addition is prime painted and the ceiling grid is in place. The bathroom tile has been laid and classroom lights have been set. The floor in the Media Center is being ground to remove old carpet glue. Prime painting is underway in the north addition corridors. Most sheetrock has been hung and taping and floating is underway on the first floor. This level should be ready for prime painting later this week. Both stairways have been set and concrete landings and infill are being poured on March 16 and 17. Plumbing down the hallways is in process. Sprinkler piping has been set. Masonry work at the east entrance to the gymnasium is underway. There is still a small bit of masonry to do at the west end of the building. Roof drains have now been connected to the storm sewer. Parking lot grading and paving is scheduled for early to mid-April. Millwork is scheduled to arrive on site April 1.


 

Photo Galleries

March 28, 2005

March 16, 2005

 

 

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster