Sheetrock work has started in the
new south addition, as well as in areas where it has been
disturbed in the existing building. Taping and finish on that
sheetrock is scheduled to start later this week. A small area
of sprinkler work remains to be completed in the existing
building. It should be complete in the next week. Scaffolding
and winter protection has been set for the balance of the
north wall of the northwest addition and that block is in
the process of being laid. Roof joists and roof deck have
been set on the majority of the south half of the north addition.
Another floor pour for the lower level of the north addition
was made today. Work continues on the under floor plumbing
for the balance of the first floor. Work continues in the
mechanical rooms with equipment being set and wiring and plumbing
being installed. The majority of the block work for the west
end of the north addition, including the stairwell, has been
set, however, focus is now on the north wall so that steel
can be set and areas dried-in. Roofing materials have been
stocked to the areas of roof deck that have been set and work
will start on drying-in those areas as weather permits.
Bitter cold has slowed down the erection
of steel, however, with the forecast moderating next week
that work is expected to resume. Work continues inside the
building on plumbing, electrical, and duct work. Sprinkler
piping in the existing building and south addition is nearly
complete. Interior block walls are being laid in the east
end of the lower level north addition, with most walls laid
in the mechanical area and underway on the telecom room, storage
room and corridor to exit. More area is being prepared for
another slab on grade pour in the lower level next week. Scaffold
is set for more block work on the west end of the second floor
north addition. Some insulation work is now starting in the
mechanical plenum, indicating that most of the piping and
ducting in that area is nearly complete. Roof deck on the
south half of the north addition is now scheduled to be installed
early next week. More extensive sheetrock work in the south
addition and in some areas of the existing building is scheduled
to start next week.
|