DISTRICT HOME
Construction HOME
Western Hillls Elem.

RELATED LINKS

Sales Tax

 
QuickLinks
About Us
Boundaries
Lunch Menu
Newcomer's Section
School Board
Transportation
Clive Construction - December 2004

Update through December 29, 2004

With the good weather this week, the job site is buzzing. Blocking and re-roofing are underway in the Media Center. Steel is being erected for the roof on the south half of the north addition. Interior block walls on the east end of the north addition are being laid. The construction of the north wall of the north addition is also underway. Finish masonry for the west end of the north addition is being placed. The east third of the floor slab for the north addition is now in place. The balance of steel for support of the west end second floor of the north addition is in place. Plumbing, electrical and mechanical work inside the existing building continues. Sheet rock for room dividing walls in the south addition has been hung and the electrical wire and switches in those walls have been placed.

Update through December 17, 2004

Work continues on the interior block walls of the north addition with walls for the art room set. Work will continue in that area next week. Steel is scheduled to start being set in some interior areas and along the south half of the north addition next week. Rough grading in the lower level is near completion and under floor plumbing in that area is underway. Some of the first floor slab may be poured late in the week of December 20 or early the following week. Re-roofing continues over portions of the existing building. Foundations for the vestibule at the northeast entrance to the gym have been placed. The northern most portion of the north addition has now been backfilled.

Update through December 10, 2004

Door frames for the south addition are now being set. Heat is being pushed into this area so that drywall work can commence. Work is underway on the sprinkler lines and duct work with most of the basic lines and duct work now installed in the mechanical plenum. Electrical work continues in the upper mechanical room. The second floor slab over the mechanical room has now been poured. Block work is underway on the second floor interior walls of the north side of the art room. The area where additional soil will be placed against the existing gymnasium has been reinforced and waterproofed and backfill is now ready to take place. Heat is now being pumped into the lower level of the north addition to dry it out so that further under floor plumbing can take place in the next couple of weeks. Block for the stairwell at the west end of the north addition is now complete up to the second level. Some rough grading has been done around the north addition to smooth out deep ruts. New roof has been placed over the old mechanical room and old music room. As weather permits, roofers will be moving to the area over the Media Center.

Update through December 3, 2004

Windows are now in the south addition. Door frames should be installed early next week and heat from the corridor should keep the area warm enough now that it is dried in to proceed with addition framing and drywall work in this wing. The air handling unit has been set and steel is now being installed to finish closing that area so that the second floor slab over that area can be poured next week. Block work for the first level stairwell at the west end of the north section is now complete and the steel should be set in this area next week to allow for decking and pouring of the balance of the second floor deck. Foundation walls and under floor plumbing work are underway in the connection between the existing building and the north section. Electrical work continues in the building. Sprinkler piping is on site and installation should start soon.

 

 

 


Photo Galleries

December 29, 2004

December 17, 2004

December 3, 2004

 

 



About Us | Calendars | Community Education | Construction Plans | Curriculum | Finance | Job Openings | Nutrition | Programs | Registration | Schools | School Board | Technology | Transportation

LINKS FOR Parents | Students | Staff Login | Job Seekers | Campus Portal | Staff Directory | Website Privacy Statement | Search | HOME

West Des Moines Community Schools
3550 Mills Civic Parkway
West Des Moines, Iowa 50265-5556
Phone (515) 633-5000 | Fax (515) 633-5099

Email Us | Email Webmaster